housing project delay: NCDRC penalises Raheja developer for
The order came on the complaint of 30 homebuyers who had sought relief from commission.
“The opposite party (Raheja developers) is directed to refund the entire amount deposited by the respective complainants along with delay compensation at 9% per annum on the deposited amount from the respective dates of deposits till realization, within a period of two months of this order. Any delay beyond two months, will attract an interest rate of 12% per annum for the same period,” NCDRC said in the order.
According to homebuyers the project is already delayed by 4-5 years and at the pace construction is on, it will take another four years to complete it.
“Haryana RERA has issued notices to Raheja for not updating quarterly progress report and changing the bank account of the project. The developer also has to pay Rs 354 crore to DTCP as it has defaulted on EDC (external development charges). About Rs 20 crore of it is for Revanta project,” said Arjun Singh Punia, a homebuyer.
The commission has